What Is Earned Value Management? A Plain-English Guide for IT Projects
Earned value management explained for IT project managers: PV, EV, AC, CPI and SPI with a worked example you can use on your next project.
Kenneth Ash
11/15/20263 min read


It's week five of a ten-week cloud migration. The status report says "on track." The budget report says you've spent about half the money. Everyone relaxes. Then week eight arrives, and suddenly you need another month and another $40,000.
The warning signs were there in week five. You just didn't have a way to see them. That's what earned value management (EVM) is for.
Earned value in one sentence
Earned value management compares three numbers — what you planned to do, what you actually got done, and what you actually spent — so you can tell early whether a project is behind schedule, over budget, or both.
Budget reports only tell you what you spent. Schedule reports only tell you what's late. EVM ties the two together, which is why it catches problems weeks before they become emergencies.
The three numbers you need
Planned Value (PV): the budgeted cost of the work you planned to finish by today.
Earned Value (EV): the budgeted cost of the work you actually finished by today.
Actual Cost (AC): what you actually spent to get that work done.
You'll also need your Budget at Completion (BAC): the total approved budget for the project.
The four formulas that matter
Cost Variance (CV) = EV − AC. Negative means over budget.
Schedule Variance (SV) = EV − PV. Negative means behind schedule.
Cost Performance Index (CPI) = EV ÷ AC. Below 1.0 means each dollar buys less work than planned.
Schedule Performance Index (SPI) = EV ÷ PV. Below 1.0 means work is getting done slower than planned.
And one forecast every sponsor will ask about: Estimate at Completion (EAC) = BAC ÷ CPI. If costs keep running the way they have, this is what the whole project will cost.
A worked example: the cloud migration
Here's the project from the opening:
Budget at Completion: $200,000 over 10 weeks
Planned by week 5: half the work, so PV = $100,000
Actually completed by week 5: 40% of the work, so EV = $80,000
Actually spent by week 5: AC = $95,000
Now run the numbers:
CV = $80,000 − $95,000 = −$15,000 (over budget)
SV = $80,000 − $100,000 = −$20,000 (behind schedule)
CPI = 80,000 ÷ 95,000 = 0.84
SPI = 80,000 ÷ 100,000 = 0.80
EAC = $200,000 ÷ 0.842 ≈ $237,500
In plain English: for every dollar spent, the team is getting about 84 cents of planned work. Work is moving at 80% of the planned pace. If nothing changes, this "on track" project will finish about $37,500 over budget — and late.
That's the week-five conversation you want to have, not the week-eight one.
Why IT projects need EVM most
IT work hides progress well. A developer can be "90% done" for three weeks. A data migration can look finished until testing finds the edge cases. EVM forces an honest answer to the question "how much value have we delivered?" instead of "how busy have we been?"
A few habits make it work on real IT projects:
Break work into small, measurable pieces. Use your work breakdown structure so each piece is either done or not done. Partial credit invites wishful thinking.
Use simple earning rules. A common one is 0/100: a task earns nothing until it's finished. Another is 50/50: half when it starts, half when it's done.
Track actual cost honestly. Include contractor hours, cloud spend and licenses — not just payroll.
Watch the trend, not one week. A single CPI of 0.95 isn't a crisis. Three weeks sliding from 0.98 to 0.90 to 0.84 is.
What to do when the numbers are bad
EVM doesn't fix a project. It tells you where to look. When CPI or SPI drops below about 0.9, ask:
Was the original estimate realistic? Unapproved work (scope creep) is a common cause.
Is a dependency or resource blocking progress?
Should the scope, schedule or budget be formally re-baselined with the sponsor?
The point is to make a decision while you still have options.
Go deeper
Chapter 11 of Maximum Delivery: Project Management Toolkit covers estimating, reserves and earned value in depth, with use cases from real IT projects and templates you can use right away. It's built as a quick-reference toolkit, so you can find the formula or checklist you need in minutes.